Political discussions about everything
#22862
The cure to global warming is almost there, just need the 34 Countries contributing to step up and provide some real money and by 2030 (if they get everything they ask for and everything goes as promised) they'll be able to save the planet...trust them. By the way Gore is a major stock holder along with George Soros, they just ask tax payers to fund the venture and they'll save us. Once they get their billions in grants, they'll cash out their stocks and by 2015 it'll all collapse because greedy tax payers stopped funding it.
One giant leap for mankind: 13bn project makes breakthrough in quest for nuclear fusion, a solution to climate change and an age of clean, unlimited energy

It may be the most ambitious scientific venture ever: a global collaboration to create an unlimited supply of clean, cheap energy. And this week it took a crucial step forward. Steve Connor reports.

An idyllic hilltop setting in the Cadarache forest of Provence in the south of France has become the site of an ambitious attempt to harness the nuclear power of the sun and stars.

It is the place where 34 nations representing more than half the world’s population have joined forces in the biggest scientific collaboration on the planet – only the International Space Station is bigger.

The international nuclear fusion project – known as Iter, meaning “the way” in Latin – is designed to demonstrate a new kind of nuclear reactor capable of producing unlimited supplies of cheap, clean, safe and sustainable electricity from atomic fusion.

If Iter demonstrates that it is possible to build commercially-viable fusion reactors then it could become the experiment that saved the world in a century threatened by climate change and an expected three-fold increase in global energy demand.

This week the project gained final approval for the design of the most technically challenging component – the fusion reactor’s “blanket” that will handle the super-heated nuclear fuel.

The original date for “first plasma” was scheduled for November 2020 but delays with the construction and commissioning phases have pushed this back to October 2022 – although some of that lost time has since been clawed back. One of the electromagnetic coils used in the giant magnets, for instance, had to be scrapped after a worker in one of the participating countries left a towel on one of the superconducting cables which then became compressed within a coil. Costly mishaps like this put the entire project behind schedule.

Rem Haange, deputy director-general of the Iter project, said that despite the delays, which are perhaps inevitable with such a huge and complex engineering project, no further problems are envisaged that could threaten the viability of the Iter project. “There are no technical issues any more that will be show-stoppers. We think we’ve overcome all the technical issues,” Dr Haange said.

Although the foundations for the main reactor building are still being laid, there has been a lot of development work off-site in the different member nations – the EU, Russia, US, China, Japan, India and South Korea. More than 90 per cent of the Iter machine’s engineering components, for instance, have now been commissioned.

These components, some the size of small houses, will be shipped by road and sea to Cadarache in the coming years, and the task of putting them together into a working machine will be formidable. Iter will have enough superconducting cabling, for instance, to wrap around the Earth 15 times.

“There are a million parts to the Iter machine and this will be the most complex and technically challenging assembly task. The tokamak reactor is 30 metres tall and consists of 18 toroidal magnetic coils weighing hundreds of tons that will each have to be positioned with a precision of less than two millimetres,” said Brain Machlin, head of Iter’s assembly operation.

As the components of the tokamak arrive in the coming years, Iter engineers will be holding their breaths to make sure the parts fit together perfectly. But even if “first plasma” happens within the next 10 years, it will still be another five years or more before they have the confidence to put radioactive tritium fuel into the vacuum vessel – and go nuclear.

Even if everything goes to plan, the first demonstration power plant using nuclear fusion will not be ready until at least the 2030s, meaning commercial reactors could not realistically be built until the second half of the century.
#23937
So we are looking at a few decades to engineer and build this machine so far and since it is now stated that the first power should be in the 2030's who thinks that they will make their new target date and even if it works as planned that it would be economically viable to provide power? Some of the components will be reaching the end of their design life before the first power is sent out of the station and I'm sure that by the 2030's the cost will have ballooned to 30 billion or more. It will never be economically viable as a project to be replicated to "Save the Planet" as they are proclaiming.
#24027
Grog wrote:Nope, dude. They are capitalists who value profit above all other considerations. Men like they built America. Great men like Vanderbilt, Carnegie, Rockefeller, Welch and Cheney.
Very shortly the right wing will start accusing Soros of funding the IRS...

:lol:

Is there a bigger cuck piece of shit?

Green Energy

You Clean energy guys shot yourself in the foot, w[…]

Secret Slut

When I was dating my wife I discovered she had an […]

Red state gun murder rate....

So that's when Sparkles was recruited as a traitor[…]

Big Beautiful Ballroom

What a putz. A sparkle pony patriot. Worthless wea[…]

Farewell Tour

Superb thread. When the history of the early days[…]

Exposing wife in phoenix

Any interested voyeurs. We are looking to expose[…]